ROBERTS AND SCHAEFER LOGO
WHO WE ARE
INDUSTRIES SERVED
SERVICES PROVIDED
LITERATURE REQUEST
PROJECT LISTS
by Industry Served
by Service Provided
FTP
PARENT COMPANY
CONTACT US
   
ROBERTS AND SCHAEFER COMPANY - How the world processes its resources
SEARCH


Thung Song 5 Cement Plant

KHD-Humboldt Wedag / Siam Cement Company
Thailand

Roberts & Schaefer Company performed all structural and mechanical design of product and clean-up (drag) conveyors, transfer chutes and dedusting systems for the Siam Cement Company's 7500 mt/d (metric tonnes per day) cement plant. R&S also provided purchase specifications for all associated mechanical and electrical conveyor components.

Conveyors ranged from 800 mm to 2400 mm in width and from 140 mt/h to 1900 mt/h capacity. In addition to the conveyors, R&S was also responsible for all material transfer chutes associated with the conveyor system. Transfer chutes and conveyors were designed to handle limestone, clay, laterite, raw meal, clinker, gypsum, cement, and coal products.

R&S was also responsible for the dedusting systems associated with the material handling systems. The project included 75 separate conveyors, eight different width clean-up conveyors, 146 transfer chutes, and 83 dedusting systems.


© Copyright 2006 Roberts & Schaefer Company. All rights reserved.
Suggestions and feedback are welcome at webmaster@r-s.com.au.