Thung Song 6 Cement Plant

KHD-Humboldt Wedag / Siam Cement Company
Thung Song 6 Cement Plant
Click Image to Enlarge Thailand

Roberts & Schaefer Company performed all structural and mechanical design of product and clean-up (drag) conveyors, transfer chutes and dedusting systems for the Siam Cement Company's 7500 mt/d (metric tonnes per day) cement plant. R&S also provided purchase specifications for all associated mechanical and electrical conveyor components.

Conveyors ranged from 800 mm to 2400 mm in width and from 140 mt/h to 1900 mt/h capacity. In addition to the conveyors, R&S was also responsible for all material transfer chutes associated with the conveyor system. Transfer chutes and conveyors were designed to handle limestone, clay, laterite, raw meal, clinker, gypsum, cement, and coal products.

R&S was also responsible for the dedusting systems associated with the material handling systems, and also prepared detailed materials lists defining equipment and materials that would either be procured locally or imported. The project included 72 separate conveyors, eight different width clean-up conveyors, 136 transfer chutes, and 68 dedusting systems.